OKTO CIDE-OS Commissioning Optics for main contractors
For main contractors

Until now you have had to take each subcontractor’s word for where they are.

CIDE-OS Commissioning Optics · Your page · Mon 16 Nov 07:30Example data
Reported complete
34of 35
Progress report · Thu 12 Nov
Proven from the plant
31of 35
read this morning · 07:30

Still to prove: chilled water, chiller changeover, fire cause and effect. Chilled water stops both witnessed tests: mains-fail on Tue 24th and fire on Wed 25th.

Chilled water
ReportedCommissioned.
The plantChiller 2 is getting 82% of its design flow. Its strainer has to be cleaned.
To prove
Chiller changeover
ReportedComplete.
The plantNot tested. It waits on chiller 2.
To prove
Fire cause and effect
ReportedComplete, ready for witness.
The plant178 of 186 lines proven. 8 wait on the door, lift and kitchen contractors.
To prove

These systems are in commissioning. What is not yet proven is a snag to finish, and it goes to both commissioning managers at the same time.

Every system on the job, read together.

CIDE-OS Commissioning Optics reads every system on the job, read-only, and checks each one against the others.

Small problems in different systems add up. That is what stops a job, and that is what it is built to find.

What you see each morning · example data

What is reported, and what is proven.

This is the page for an example hospital ward block, 16 days from completion. The figures are example data.

Example of the page a main contractor sees each morning: on-target score, where you stand, the date, the money and the evidence. Example data.
Your page on a phone · where you stand and whose package · example data
Reported and proven

34 systems reported complete. 31 proven.

The page sets each progress report beside what the plant reads, system by system. Where a system is not yet proven it says what is left to do and who it is waiting on.

Whose package

The chiller 2 trip belongs to the mechanical package.

Six readings from four systems, in time order. The pump was at full speed and its power was normal. The pressure drop across the strainer was 41 kPa, against 12 on chiller 1. The strainer has to be cleaned. A strainer that dirty this late in the job means the clean of the chilled water system should be checked as well.

The integrated systems test

The fire test would not pass today on 8 of 186 lines.

3 doors do not release, 2 lifts do not return to the ground floor, and 3 lines at the kitchen canopy cannot be tested. Each is listed with the contractor and the date he promised. The test is witnessed on Wed 25th. The page also shows which revision of the cause and effect matrix was tested, and that the fire alarm, smoke control, firefighting lift and emergency lighting stay up on the generator. On a hospital it also shows the AHUs for critical rooms that have to keep running when the fire alarm operates.

The date

2 December holds if chiller 2 is proven by Wednesday night.

If it is not, the mains-fail test moves to Fri 27th and the fire test to Mon 30th, with no days in hand. A week late on this job costs £355,000 in damages and prelims. That figure is example data. On your job it is your own.

Your page

One page for the job: on target or not, and is the plant doing what it was designed to do.

Every reading, test and sign-off on the job ends up on one page, whoever's package it sits in. It counts the systems through seven levels, L0 to L6. You have it before the progress meeting.

This is the rest of the page for the same example hospital, as it reads on a phone. It shows what is waiting on chiller 2, what happens next, what would fail if the integrated systems test ran today, the seven steps to the completion certificate, what the plant measures against design by trade, and the level of completion.

Your page on a phone: What is waiting on what · what happens next. Example data.
What is waiting on what · what happens next · example data
Your page on a phone: The integrated systems test · the road to the completion certificate. Example data.
The integrated systems test · the road to the completion certificate · example data
Your page on a phone: Is the plant doing what it was designed to do · level of completion, L0 to L6. Example data.
Is the plant doing what it was designed to do · level of completion, L0 to L6 · example data

The page carries on with what would fail if the integrated systems test ran today, the seven steps to the completion certificate, and the level of completion.

Why you need it

The evidence sits between the systems. CIDE-OS shows it to you.

Evidence from every system, with the time on it.

At the end of a job every trade tells your commissioning manager the same thing: “ours is done, it’s waiting on someone else.” Each one is probably right about their own system. Nobody can see across all of them.

CIDE-OS Commissioning Optics reads the M&E and technology systems together, read-only, on one clock. Each morning it shows you which systems reported complete are proven from the plant, which package a failure belongs to, and which lines of the witnessed tests would not pass today.

Two weeks before handover

Levels 5 and 6 are cold. Four trades each say it is not them. All four are right.

Without it
A day and a half
to find one loose power lead.
4 trades
pulled in one after another, each proving it was not them.
2 cold floors
overnight, with the client’s fit-out team working in their coats.
With CIDE-OS Commissioning Optics
2 minutes
from the problem to a report naming the switch and the cabinet.
1 electrician
sent straight to the lead. Fixed 16 minutes after it came out.
No cold floors
The lead was back in on the Friday afternoon. The floors were warm on Monday.

Monday, 08:30. The client’s fit-out team on levels 5 and 6 are in their coats. The heating plant is running, the pipework is hot, and every other floor is fine.

08:45. The site manager calls the BMS contractor. Their engineer logs in remotely and comes back an hour later. Forty-two FCU controllers on levels 5 and 6 are showing offline, and with no signal, their heating valves have closed. “It’s not us. The controllers have dropped off the network. Probably power.”

10:15. It usually is the sparks if it isn’t the BMS, so the electrician is pulled off his snag list. He checks the FCU distribution boards on both floors. Every breaker is on and the boards are carrying load. He checks a few FCUs at the ceiling, and they have power. “It’s not us.”

11:30. Someone emails the IT contractor. They aren’t on site, because they support dozens of sites remotely. The reply arrives at 15:40. “We haven’t changed anything. The switches on that site aren’t monitored until the service contract starts at handover. Can someone on site check the comms cabinet?”

16:10. Nobody is sure which cabinet serves levels 5 and 6. The key is found and the riser cupboard is opened. All the lights are on and the cabinet looks fine. The floors stay cold overnight.

Tuesday, 08:20. The electrician goes back with the riser drawings and looks again, unit by unit. Everything is flashing except the second switch from the top. It’s completely dead. Its power lead has been pulled half out of the back. The painters moved the rack a few inches on Friday afternoon to get behind it.

08:30. The lead is pushed home and clipped. The controllers come back online, the valves open, and by mid-morning levels 5 and 6 are warm. It took a day and a half, four trades and a lot of phone calls to find a plug that had come loose.

What CIDE-OS Commissioning Optics does

It reads the BMS, the network switches and OKTO’s current sensors on the distribution boards, all read-only and on one clock. The IT contractor gives it read-only access to the switches at the start of commissioning, so it is watching them before their own monitoring begins. The same problem, with it on site, on the Friday afternoon:

Report · Friday 14:3942 FCU controllers on levels 5 and 6 went offline at 14:37. Their heating valves will close and the floors will lose heat. The FCUs have power, because their distribution boards are carrying normal load. At 14:37 access switch SW-R2-02 in the level 5 riser cabinet stopped responding, and the controllers dropped off the network within a minute. At the same moment the cabinet’s supply current dropped by a small step, while the circuit stayed live and the other switches in the cabinet kept answering. The switch has lost its own power inside the cabinet.ActionCheck the power lead on SW-R2-02, the second switch from the top in the level 5 riser cabinet.

The electrician is in the riser two floors away. He pushes the lead home at 14:50, and the controllers are back by 14:53. On Monday morning levels 5 and 6 are warm.

Nobody had to phone anyone or wait on a ticket. It took a few minutes, not a day and a half.

Every trade said it wasn’t theirs. CIDE-OS showed what happened.

The same problem, read by three people

The electrician

Check the power lead on SW-R2-02, the second switch from the top in the level 5 riser cabinet.

The commissioning manager

42 FCU controllers on levels 5 and 6 went offline at 14:37. The cause is one network switch that has lost its power inside the cabinet. It is not the BMS and it is not the distribution boards.

You

Levels 5 and 6 will be cold for the client’s fit-out team on Monday unless one power lead is put back today. The electrician is two floors away.

Six weeks before handover

Level 4 keeps going warm. Never for long, never when anyone is there, and every system says it’s fine.

Without it
Weeks
of a problem that comes and goes, with the date getting closer.
3 trades
each checked their own kit, found it healthy and closed it out.
Nobody owns it
Windows and sensors get the blame.
With CIDE-OS Commissioning Optics
3 occurrences
were enough. Every one was recorded to the second and lined up.
1 cause named
the undervoltage setting on one pump inverter.
1 setting changed
Level 4 does not go warm again.

It starts as a complaint from the fit-out team on level 4. Some afternoons the floor gets stuffy for a few minutes, then it’s fine again. By the time anyone gets up there, it’s fine.

The BMS engineer checks his trends. He sees short rises in room temperature, two or three times a week, always after lunch. His sequences are right and his valves are open. Every time, he finds nothing wrong.

Mechanical check the chilled water. They see the flow dip for a few seconds now and then, but the pumps are healthy and the system is full and vented. It looks like a pump hunting, so they check the settings and close it out.

Electrical check the boards. Nothing has tripped and there are no faults.

Every trade has looked, proved their own kit and ruled themselves out. Weeks go by. Someone suggests the client’s people are opening windows. Someone else blames the sensors. It becomes the problem everyone knows about and nobody owns, while the date gets closer.

Anyone who has been at the end of a job knows this one. A fault that comes and goes is the hardest kind to find, because you’re never there when it happens.

What CIDE-OS Commissioning Optics does

It reads the BMS, the mechanical readings and the power at the boards from OKTO’s own sensors, all on one clock, to the second. It doesn’t wait for someone to be standing there. It sees every occurrence and lines them up.

After the third time, the pattern is plain:

ReportThe level 4 temperature rises on 4, 6 and 11 November all follow the same sequence. Chiller 2 starts its second compressor. The plant room board voltage dips for under half a second. The inverter on chilled water pump CHWP-2 trips and resets itself within six seconds. Flow to level 4 drops, and room temperatures rise before recovering.ActionPlease ask electrical and the pump supplier to check the undervoltage setting on the CHWP-2 inverter.

One setting is changed on the inverter. Level 4 doesn’t go warm again.

Every trade said it wasn’t theirs. CIDE-OS showed what happened.

More examples

Eight more, from different trades. In each one, every system passed its own tests.

It happens wherever one system sits between two trades and each trade only checks its own. Select one to open it.

Fire alarm, BMS and dampers · four weeks before handoverEvery few weeks, on a Thursday, two occupied floors lose their fresh air. Nobody can work out why only then.

The building is in partial occupation. The client's first tenant moved onto levels 4 and 6 last month, while commissioning carries on around them on the other floors. The fire alarm is live and the building is being run for real, with the facilities team learning the systems as they go.

Every Thursday, Jeff from the fire alarm contractor does the weekly fire alarm test, as the standard requires. He sets off one call point, checks the panel and the sounders, and resets it. It takes ten minutes.

Jeff does it at 07:45, before the trades arrive. At that time the air handling units are still off, because their time schedule starts at 08:30. The fire signal has nothing to stop.

Every third Thursday, Jeff has his kids on the Wednesday night and takes them to school. He gets in at ten and does the test at 10:15.

By 10:15 the air handling units are running. The fire signal does what it should. It stops the units and closes the fire and smoke dampers. Jeff resets the panel at 10:18 and the test is logged as a pass.

The BMS does what it should too. Thirty seconds after the reset, it restarts the units. But the motorised dampers take ninety seconds to drive fully open. AHU-2 and AHU-4 start against dampers that are still closed, the duct pressure spikes, and their high-pressure safety switches lock them out. Those need a manual reset.

The BMS logs the alarms: dampers not proven open, high duct pressure and AHU lockout. But it's four weeks before handover, and the alarm list has over a thousand entries. There are points still being commissioned, sensors not yet calibrated, plant on hand for testing and floors still being fitted out. Every few minutes another alarm arrives and another one clears. Nobody can see three important alarms in that list, and nobody is looking for them.

Levels 4 and 6 have no fresh air for the rest of the day. By early afternoon the tenant's office manager is on the phone to the client, and the client is on the phone to you. The BMS engineer finds two units locked out, resets them and can't see why. Mechanical check the fans and belts and find nothing wrong. The fire test passed. Three weeks later it happens again.

Every system did what it was designed to do. The problem is between them, and it only shows when the test is done at a different time.

What CIDE-OS Commissioning Optics does

CIDE-OS reads the fire alarm, the BMS and the damper positions on one clock. It knows which plant is still being commissioned and which is meant to be running for a tenant, so it picks the three alarms that matter out of the thousand. It sees every Thursday, not just the bad ones, and after the second time it lines them up:

ReportAHU-2 and AHU-4, serving occupied levels 4 and 6, locked out on high duct pressure at 10:19 on 22 October and 12 November. Each time it was one minute after a fire alarm test reset, while the units were running. The BMS restarted them 30 seconds after reset, but the fire dampers took 90 seconds to open. On the other Thursdays the test was at 07:45, with the units off, and nothing tripped.ActionPlease ask the BMS contractor to hold the AHU restart until the dampers show open. Until then, keep the weekly fire alarm test before 08:30.

The restart is changed to wait for the dampers. Jeff can test whenever he gets in, and the tenant never notices again.

Every trade said it wasn’t theirs. CIDE-OS showed what happened.

Generators, pumps and chillers · the power failure testThe power failure test was stopped after ten minutes. Three contractors each say their part worked. All three are right.

Near the end of every large job there is a power failure test. The mains is switched off to prove the building keeps running on its generators. The client, the consultant and every trade are in the building to watch it.

The generators start and take the load inside the time. Electrical are happy.

Ten minutes in, the cooling has not come back and the test is stopped.

The BMS contractor checks first. His software ran as written. Mechanical say the pumps and pipework were tested weeks ago. Electrical say the changeover to the generators worked.

Nobody did anything wrong. Now three teams are going through three sets of records, each with a different clock, trying to match them up by hand. It takes two days to agree what happened. The chilled water pumps are on a board that loses power for a few seconds at changeover, and they were slow to start again. With no water flowing, the chillers shut themselves down and then waited out their restart timer.

The test has to be booked again, with the client, the consultant and every trade back on site.

All the information was there. The power system recorded when the board changed over, the BMS recorded when the chillers shut down, and the pumps recorded when they stopped and started. Nobody was reading the three together.

That is what we have built CIDE-OS Commissioning Optics to do. It reads all three on one clock and puts what happened in order. Before anyone has left the building, the commissioning manager has this:

ReportPower failure test stopped at step 3. Board EB-2 changed over at 10:02:14 and chilled water pumps 1 to 3 lost power. Chillers 1 and 2 shut down on low flow at 10:02:31. The pumps started again at 10:03:40, but the chillers were held off by their restart timer.ActionBefore the test is run again, look at how the pumps restart after changeover, with electrical and the BMS contractor.

The fix is agreed that afternoon and the test is run again the same week.

Every trade said it wasn’t theirs. CIDE-OS showed what happened.

The same problem, read by three people

The electrician

Chilled water pumps 1 to 3 lost power when board EB-2 changed over, and took 86 seconds to start again. Please look at it with the BMS contractor.

The commissioning manager

The test failed on cooling, not on power. The generators started inside the time. The pumps were slow to start again and the chillers waited out their restart timer.

You

Today's power failure test has failed and cannot be run again today. The generators passed. The fix is to how the pumps restart. Agree it this afternoon and book the client and the consultant again for this week.

Pump, valve and BMS · six weeks before handoverThe heating does not work. Three contractors have each done exactly what they were paid to do. All three are right.

On every job there is a controls document called the description of operations. It is what a BMS contractor priced to do and what he gets paid against. It might simply say: when a room needs heat, open the valve and turn the pump on.

So the BMS contractor opens the valve and turns the pump on. Job done, by the letter. We have been that BMS contractor for many years.

The pump does not run, so it becomes mechanical's problem. Then it becomes electrical's problem, because during testing there was no power to a pump halfway up the building. Each of them is flat out on their own part. Nobody did anything wrong.

Nobody finds out until the next day, when somebody walks the building and works backwards.

Multiply that across every system in the last six weeks before practical completion, with damages running. That is why the end of a job turns into a scramble.

The odd part is that the answer is already in the building. The BMS knows the valve opened. It can know the pump did not run. It can know the supply to that pump is off. Nobody is reading those three things together.

That is what we have built CIDE-OS Commissioning Optics to do. It reads them together and tells the commissioning manager the same day, in plain English:

ReportValve opened. Pump did not run. Supply to the pump has possibly tripped.ActionPlease look at pump B2-2206.

Your BMS will alarm on that pump. So will a thousand other things that week. CIDE-OS Commissioning Optics reads them together and tells you the one that matters, and why.

Every trade said it wasn’t theirs. CIDE-OS showed what happened.

The same problem, read by three people

The electrician

No supply to pump B2-2206. Please look at it.

The commissioning manager

Floor 22 heating cannot be balanced tomorrow. It is waiting on power to one pump.

You

Thursday's witness for floor 22 will be lost unless power is on by 3pm today. Decide whether to move him.

Access control and ITThe doors that lock everyone out at 7am.

Every morning for a week, the staff entrance readers reject every card for about ten minutes, and then they work fine. The access control contractor says the readers and controllers pass every test. IT, who are remote, say nothing has changed. The sparks say the power is on. CIDE-OS shows the door controllers rebooting at 06:58 each day, the moment the cleaners plug a floor scrubber into the same socket circuit as the controller power supply. The controllers restart faster than the network switch, can't reach the card database, and reject cards until they resync. Cause: the controller supply is on a general socket circuit instead of its own fused spur.

GasThe kitchen that keeps cutting out.

The new staff restaurant's gas ranges cut out mid-service on random days. The catering supplier says the appliances are fine. The gas engineer says the supply pressure is fine, and the sparks say the extract fan has power. The black box is the kitchen gas interlock, which shuts the gas valve if it can't prove the extract airflow. CIDE-OS reads the interlock panel, the extract fan current and the gas valve status together. The gas cuts out within seconds of the extract fan being turned down, every time the chefs lower it to quiet the canopy. Cause: the airflow switch is set just above the airflow at low speed.

ElectricalThe UPS that runs out before the generator arrives.

During the generator test, the comms rooms on levels 2 and 3 go dark, yet the UPS shows healthy and the generator runs perfectly. The UPS supplier blames the generator, the generator supplier blames the changeover switch, and the sparks blame the UPS. CIDE-OS lines up the mains failure, the generator start, the changeover and the UPS output current on one timeline. The batteries ran flat at 4 minutes, and the changeover didn't switch to the generator until minute 6. Cause: the changeover still has a long delay left from factory testing, and the batteries were never fully charged after installation.

WaterThe booster set that starves the top floors.

At lunchtime, the top two floors lose water pressure and the toilets fill slowly. The plumber says the pipework is fine, the sparks say the booster set has power, and the booster supplier says their unit is healthy. CIDE-OS reads the booster pump currents, the break tank level and the incoming water meter. At peak demand the break tank empties faster than the mains refills it, and the pumps stop on low tank level. Cause: the valve feeding the break tank was left partly closed after flushing.

Heat pumpsThe black box in the middle.

The roof heat pumps lock out on cold nights, so the building is cold in the morning. The heat pump supplier says the system is the problem. The mechanical contractor says flow is fine, and the sparks say there's power. CIDE-OS reads the heat pump fault codes, the pump currents and the outside temperature. Each lockout happens during a defrost cycle, a few minutes after the circulating pump has slowed for the night. Cause: the night setback drops the flow below what the heat pump needs to defrost, so it trips on low flow.

Next step

See it on a screen, or send us the drawings.

20 minutes with you and your commissioning lead. Philip will come to you, or you can see it working in Lisburn. If you have a job going into commissioning in the first half of 2027, send us the drawings for a fixed price.

The difference

Checklist tools record what people type in. CIDE-OS Commissioning Optics reads the plant and every other system on the job, power at the boards, isolations, who shut what, your programme and snag list, and what the whole job is waiting on.

CIDE-OS Commissioning Optics reads the plant, whatever is there and whoever installed it. Nothing is taken out or replaced.

It does not matter which package the problem started in. It tells the person in charge what it means for the date.

CIDE-OS reports what the readings show. It is read-only. Every report has the readings and the times behind it.

There is no generative AI in it. The same readings give the same report every time. Every sentence can be traced to its readings, its rule and its time. A report that could read differently tomorrow is no use in a dispute.

Commissioning or complete

During commissioning nothing is a fault. It is a snag, until the system is issued as complete.

At this stage plant is switched off, in hand and under test every day. That is commissioning, and CIDE-OS Commissioning Optics treats it as commissioning.

It knows which systems are still in commissioning and which have been issued as complete. While a system is in commissioning, what it finds goes to the commissioning manager as a snag to finish.

It knows this from the commissioning record. Each system moves through seven levels, L0 to L6. Until your commissioning manager issues a system at the last level, it is in commissioning.

Once a system is issued as complete, the same thing is reported as a fault.

What it reads

All of these, on one job.

M&E. Mechanical, electrical, plumbing and balancing.

Life safety. Fire alarm. Smoke control, smoke vents and fire dampers. Sprinklers, wet risers and fire pumps. Emergency lighting.

Power. SCADA power. UPS. Generators and fuel. Solar, batteries and EV charging. Energy and water metering.

The building. Access control. Doors and door hardware. Vertical transportation. Lighting controls. Window treatment. Air quality. Leak detection and water quality.

Technology. AV and IT.

By type of building. Kitchen ventilation and refrigeration. Guest room management. Medical gases and nurse call.

Plant with no monitoring yet

During commissioning a lot of the job is not monitored by anyone. We bring our own sensors and network to read it.

Power

Our own wireless current sensors.

We fit wireless current sensors on the distribution boards and on plant that has no monitoring yet. They show whether a board, a pump or a cabinet is drawing its normal load, and the time it changes.

The network

Read-only access to the switches.

The IT contractor's own monitoring usually starts at handover. He gives us read-only access to the switches at the start of commissioning, so they are read from that day.

Our own network

On site before the building's network.

While the building's network is going in we run our own beside it. We bring it and we take it away.

Example

It is how the cold floors were traced to one power lead.

The BMS showed 42 controllers offline. The switch readings showed which switch had stopped. The current sensor showed a small step down on the cabinet supply at the same moment, while the cabinet stayed live.

How it is read, and who runs it

The readings come from the plant. We run it, and your team reads the page.

How the readings get in

Read from the systems already on the job.

CIDE-OS reads each system the way it already talks: the BMS on BACnet, power meters on Modbus, network switches on SNMP. It is all read-only.

Keeping it up to date

Nobody types the readings in.

The readings come from the plant, so they are current without anyone on your team updating them.

The rules

Agreed with your commissioning manager before they are used.

The rules say what depends on what on your job. We write them down with your commissioning manager and he signs them off before they are used. When the design or the programme changes, we change the rules.

Who runs it

We do. There is no new job for your team.

We connect the systems, fit the sensors, write the rules and run it through commissioning. Your team reads the page.

What you get

The date, the proof and the record, with nothing new for your teams to fill in.

Completion

Proof for completion, taken from the plant.

Every fire, smoke control and ventilation test is logged as it happens: what was tested, when, by whom and the result. The page shows the seven steps to the completion certificate and where each one stands: the cause and effect matrix frozen, each system proven, the integrated systems test, the commissioning notice, the fire safety information and the inspection. Sign-off is most often held up by a matrix that is not frozen, life safety that is not proven on the generator, or fire safety information that is not ready. The page shows where each of those stands. It supports your evidence for Building Control, and for Gateway 3 on a higher-risk building. It does not replace the documents Building Control or Gateway 3 require.

Who held whom

Recorded at the time, with the dates.

What was asked for, when it was asked and how many days passed. It supports a delay notice and an extension of time. It does not replace the notice your contract asks for.

Across packages

Cause and effect, proven line by line.

Fire alarm, smoke control, lifts, doors and access control sit in different subcontracts. CIDE-OS shows which lines are proven, which are not and which package each one is waiting on.

The offer

Your first job is half price.

Pick one of your jobs going into commissioning in the first half of 2027. CIDE-OS Commissioning Optics is priced per square foot, per building.

Your first job is half that price. Send us the drawings and you have a fixed price within five working days.

What we need from you

Four things from you.

Read-only access to all the technical systems on the job, not only the BMS. We write the request for each contractor and you send it, and we help each contractor with the technical side. A named commissioning manager. The programme. Somewhere for our kit. We fit our own wireless sensors, under your permits, and we write the RAMS. Set-up depends on the size of the job. Expect one week for the BMS and our sensors. The other systems are added as each contractor gives us read-only access. That access is the critical path, and we will need you to drive it.

Your own figures

See your job on the page before you decide.

Give us three figures from one job: damages per week, prelims per week and the completion payment. We show you your page with those figures in it.

Three jobs

We are only taking on three jobs in the first half of 2027.

Our own engineers will be on your site, so we are keeping it to three and doing each one properly. You appoint us direct and our contract is with you.

After handover

Your client can keep it.

CIDE-OS Commissioning Optics runs on the same CIDE-OS that the Belfast Trust uses. At handover your client can keep CIDE-OS on the building, on its own agreement with OKTO. It starts with the commissioning record of every system, so a fault in the defects year is checked against what was proven. On a new hospital, the same CIDE-OS is what the command centre wall shows.

Why we can do this

We write the software and we commission the plant. Most firms do one or the other.

Since 1992

34 years at the end of jobs.

We have commissioned building controls since 1992, the last twelve years mostly on London jobs under main contractors, with our own directly employed engineers. Every site problem CIDE-OS is built to catch happened on our last London job. Our engineers found each of them the hard way.

The Belfast Trust

The software already reads 245,071 points.

CIDE-OS is running the digitisation of the Belfast Trust estate across the Royal and City sites. It reads the BMS, SCADA, generators, boilers and sterile services that were already on the estate. About 2,900 of the points carry the rules, and each one is checked before it is used.

Our commissioning, not a CIDE-OS installation

"The factory acceptance tests we have been involved with the last couple of days have been a resounding success and cement the positive influence OKTO have had on the Peninsula project. OKTO have continued to outperform the norm at every turn."

Matt Howe · Building Services Manager · Sir Robert McAlpine · The Peninsula London

This is about our commissioning work at The Peninsula London, not a CIDE-OS installation. We can arrange a reference call about that work.

We can also arrange a reference call with the Belfast Trust.

You can also see it working at OKTOLabs in Lisburn.

Trusted by · Sir Robert McAlpine · The Peninsula London · Schneider Electric · Allstate

Your own tools

Keep the tools you already use. CIDE-OS reads from them.

Your programme, snag list and commissioning records stay where they are.

Programme

The dates and what is critical.

Asta Powerproject, Primavera P6 and Microsoft Project.

Snags and site records

What is open and how long it has been open.

Procore, Autodesk Construction Cloud, Fieldwire, Dalux and Viewpoint Field View.

Commissioning records

What has been tested and witnessed.

CxAlloy, Facility Grid and CxPlanner.

Handover and golden thread

CIDE-OS sends its record to them.

Zutec, Createmaster and Dalux Handover.

Permits

Which plant is released.

Your own permit system. CIDE-OS never replaces a permit or a lock-off.

Anything else

A spreadsheet upload.

It works on every job from the first day.

Your questions

Questions you will ask.

Independence

It reports readings and logged tests.

CIDE-OS reports what the plant read and what was tested, with a name and a time. On your job we are not the BMS contractor.

Safety

It is read-only and controls nothing.

It cannot switch, set or override anything. It never replaces a permit or a lock-off. Safety interlocks stay live.

The record

It belongs to you.

Our contract is with you, so the record is yours. You decide who sees the record and what goes to your client. The data is held in the UK. Our digital building work is Cyber Essentials Plus certified. We are ISO 9001 certified. It is designed in line with ISO 27001 and ISO 19650-5. We are not ISO 27001 certified. Professional indemnity details are available on request.

The fire alarm

It is read one way. Nothing can be sent back to the panel.

Every event leaves the panel through a specialist fire alarm monitoring system and is passed on to CIDE-OS. Each event names the device, what happened and the time to the second. The doors, dampers, lifts and plant are read from their own systems. CIDE-OS sets the two side by side, and that is how a cause and effect line is shown as proven. The fire alarm contractor has to agree to the monitoring system being connected.

Your M&E contractor

It is not there to catch him out.

His balancers, mechanical team and electricians each get a screen of their own, and his commissioning manager is told at the same time as yours when something on his package is off. He sees his own package. The record across every package is yours. It also shows the days he is waiting on another package. We will take your commissioning managers through those screens separately.

The detail, for your commissioning managerHow we work, and how to see it working. Select to open.
How we work

To do this you need people who have commissioned buildings, software that already reads a whole estate, plain English a director can act on, and your own network on site before the building's is ready. We have all four.

The rules

Written down with the engineers who know the plant.

At Belfast we sat with the Trust's engineers and wrote down what depends on what, one area at a time, and they signed it off before it ran. On your job the same method sets out what has to happen before what.

Plain English

One sentence for the person in charge.

We also designed and built the Trust's estates command centre at the Royal Victoria Hospital: four desks, built to ISO 11064, the standard for control rooms. The director gets one sentence: what is at risk, how long there is and what needs deciding. The detail for his managers and the readings for his engineers sit under it. Your page is built the same way.

Before site

Tested in Lisburn first.

Every system we deliver is built and tested in OKTOLabs before it reaches site: eight test phases, including a full power-cycle test and a two-week soak. Faults are found in Lisburn, months before they would be found on site.

See it working

Come to OKTOLabs in Lisburn for a morning, with your commissioning lead. We’ll run our test rigs with real plant running and software simulations - You’ll read what CIDE-OS says about each, with the times.

In Belfast

See it on a whole estate.

We can arrange a visit to the estates command centre at the Belfast Trust, where CIDE-OS reads 245,071 points across two hospital sites.

Next step

Can we have 20 minutes with you and your commissioning lead to show it on a screen?

Your first job is half price. Philip will come to you, or you can see it working in Lisburn.

Philip Dowds · Managing Director · OKTO Integrated Services Ltd

Lisburn office +44 (0)28 9266 7030 · Philip's mobile +44 (0)7860 356124

[email protected]

Unit 1 Crescent Business Park · Lisburn BT28 2GN

London office · 25 Wilton Road · Pimlico

www.oktotechnologies.co.uk

Schneider EcoXpert · Tridium Niagara · BCIA · Safe-T-Cert · ISO 9001 · Cyber Essentials Plus

OKTO Integrated Services Ltd · Lisburn · London · Registered in Northern Ireland NI691500
OKTO